- Location
- India
- Year
- 2025
- Commercial Model
- CAPEX
- Type
- Ground-Mounted Solar
- Capacity
- 1 MWp
Designed for a high-dust mining environment with an 11 kV HT evacuation system, delivered from design to commissioning in a 45-day window.
Highlights
- Designed for a high-dust mining environment, with durability and long-term generation performance as key priorities.
- Built an 11 kV HT evacuation system to move power efficiently over distance.
- Sized and routed cables with protection and reliability across the full transmission route in mind.
- Completed design, installation and commissioning in a 45-day window.
- Adjusted module layout and tilt to improve generation under difficult site conditions.
- Provided earthing and lightning protection suited to an exposed mining-site environment.